The boiler being removed was only 2 years old. Installed by a local contractor and serviced by a local oil company. Like any job things went wrong. The site lost power and theses guys had to work off the head lights of their van. To add to that the supplier was missing an eccentric fitting so a trip out of state was made.
Notice the nice strapping on the copper lines...
Hammer time!
The old feed tank
The old burners fire box. Poor service by the local oil company
Old boiler section, only two years old
The new boiler going in
"Combustion, I set the burner for a trace of smoke with a positive breech pressure, CO was about 33PPM, CO2 was 12.2% and I can't remember the rest."
"There are a few things on order to finish the job including insulation, a second LWCO and a manual reset high limit"
The guys from Temprite came through with quality work on short notice